HomeMy WebLinkAboutZ-3459 Staff Analysis}E } March 25, 1980
Item N0. 10 - Z-3459
Owner:
Applicant:
Request:
Purpose:
Existing Zoning:
Location:
Site Characteristics:
Size:
Existing Land Use:
Abutting Land Use
Zoning:
Zoning History:
Applicable Regulations:
Martin Industrial Park, Inc. and
George C. Martin, Trustee
W. S. Mitchell
Rezone to "C-3" General Commercial
and "I-2" Light Indsustrial
Mixed use development
"R-2" Single Family
Southeast corner of I-30 and
Mabelvale Interchange
Wooded
119.65 acres +
Large vacant area, having only
Mr. Martin's house
North - Public, Zoned "R-2"
South - Residential, Zoned "R-2"
East - Vacant and Industrial,
Zoned "R-2"
West - Residential, Zoned "R-2"
None
Zoning and Subdivision Ordinances
FACTUAL INFORMATION
March 25, 1980
Item 10
1. NEED AND/OR DEMAND
This tract abuts the I-30 frontage road on the north
and the Missouri Pacific Railroad on the south. The
property just to the east was recently zoned to
a combination of commercial and industrial districts.
There is no specific proposal for development at this
time.
2. COMPATIBILITY WITH MUNICIPAL PLANS
Only the commercial portion of the request is not
compatible with the extraterritorial plan. This plan
calls for the entire tract to be used for industrial
purposes in the long term.
3. EFFECT ON ENVIRONS
While no truly environmental impacts are expected,
there seems to be no doubt that the eventual
development of this 119 acre tract will have
significant meaning for the surrounding properties.
There is no particular expectation that the future
impacts will be especially harmful.
4. NEIGHBORHOOD POSITION
No neighborhood position has been expressed.
5. PUBLIC SERVICES/EFFECT ON
No adverse comments have been received.
6e UTILITIES/EFFECT ON
No adverse comments have been received.
7. EFFECT ON PUBLIC FINANCES
Logically, one must assume that the development of this
property would add significantly to the City's tax
base. Offsetting public costs would be minimal.
8. LEGAL CONSIDERATIONS/REASONABLENESS
This property abuts property recently zoned for the
same combination as is being requested. Surrounding
land uses suggest its appropriateness, and the
March 25, 1980
Item No. 10 - Continued
extraterritorial plan indicates this area for
industrial development. Staff is concerned about the
proposal for "C-3," feeling that access is not quite
what is anticipated to be needed to serve 45 acres of
commercial development.
9. STANDARDS OF QUALITY
No standards of quality have been addressed.
10. TRAFFIC AND STREET RIGHT-OF-WAY
The only right-of-way issue is Mabelvale Pike. It is
carried as a minor arterial on the Master Street Plan,
requiring an 80' right-of-way. Staff estimates that
the applicant would be required to provide an easement
deed for ten feet. He has agreed to do so. Access to
the commercial -portion of the request is problematical,
due to the design of the Mabelvale Interchange.
ANALYSIS
The extraterritorial plan indicates that this area should be
developed for industrial use. Access to the commercial
development proposed appears inadequate. The addition of 45
acres of commercial zoning to the 20 acres recently
committed to the east seems excessive.
STAFF RECOMMENDATION:
Staff recemmends approval of the "I-2" portion of the
request as filed and a recommendation for approval of
"I-1" on the portion requested for "C-3" General
Commercial.
COMMISSION ACTION:
The applicant was present, and there were several objectors.
Mike McManigal speaking for several neighboring property
owners on Mavis Circle and Mabelvale Pike presented a
petition containing a number of signatures of neighboring
residents which requested that the rezoning request be
denied. In support of their request, he provided a lengthy
statement of problems that exist within their residential
neighborhood regarding traffic and road conditions and
March 25, 1980
Item No. 10 - Continued
especially drainage problems which they felt would be
exacerbated by the approval of this application.
Following the Presentation by Mr. McManigal, the applicant
represented by non Venhaus, discussed the extraterritorial
plan and its meaning relative to this case. He discussed
the proposal that when the property is developed, the
questions raised by the neighbors in opposition would be
addressed appropriately by the engineering considerations
that would be necessary.
He stated that the sewage problem would also be handled at
the time of development and further argued against the staff
recommendation for "I-1" Light Industrial instead of the
"C-3" General Commercial requested and pointed out the
proximity to a case wherein "C-3" had been approved only one
month before.
FollowiUg Mr. Venhaus' presentation, another neighbor,
Phyllis Bearden, also Qf Mavis Circle further discussed
drainage problems as they related to her property and stated
the view of the neighbors that commercial was not needed in
that area, that more than adequate property did exist, and
asked that it be denied. A lengthy discussion ensued.
Several negotiated points of settlement between the
applicant and the neighboring property owners were offered
and considered. Some were rejected, and some were
considered to require additional negotiation, and on that
basis after the discussion period had evolved for the better
part of an hour, the Commission moved to defer consideration
to of the application to April 29 to allow more careful
consideration by staff, the neighbors and the applicant
prior of a final solution of this situation. The motion was
passed - 5 ayes, 3 noes and 0 absent.
April 29, 1980
Item No. 5 - Z-3459 - DEFERRED
Owner: Martin Industrial Park, Inc. and
George C. Martin. Trustee
Applicant: W. S. Mitchell
Request: Rezone to "C-3" General Commercial
and "I-2" Light Indsustrial
Purpose: Mixed use development
Existing Zoning: "R-2" Single Family
Location: Southeast corner of I-30 and
Mabelvale Interchange
Site Characteristics: Wooded
Size: 119.65 acres +
Existing Land Use: Large vacant area, having only
Mr. Martin's house
Abutting Land Use North - Public, Zoned "R-2"
Zoning: South - Residential, Zoned "R-2"
East - Vacant and Industrial,
Zoned "R-2"
West - Residential, Zoned "R-2"
Zoning History: None
Applicable Regulations: Zoning and Subdivision Ordinances
FACTUAL INFORMATION
April 29, 1980
Item 5
1. NEED AND/OR DEMAND
This tract abuts the I-30 frontage road on the north
and the Missouri Pacific Railroad on the south. The
property just to the east was recently zoned to
a combination of commercial and industrial districts.
There is no specific proposal for development at this
time.
2. COMPATIBILITY WITH MUNICIPAL PLANS
Only the commercial portion of the request is not
compatible with the extraterritorial plan. This plan
calls for the entire tract to be used for industrial
purposes in the long term.
3. EFFECT ON ENVIRONS
While no truly environmental impacts are expected,
there seems to be no doubt that the eventual
development of this 119 acre tract will have
significant meaning for the surrounding properties.
There is no particular expectation that the future
impacts will be especially harmful.
4. NEIGHBORHOOD POSITION
Several neighbors have expressed opposition.
5. PUBLIC SERVICES/EFFECT ON
No adverse comments have been received.
6. UTILITIES/EFFECT ON
No adverse comments have been received.
7. EFFECT ON PUBLIC FINANCES
Logically, one must assume that the development of this
property would add significantly to the City's tax
base. Offsetting public costs would be minimal.
8. LEGAL CONSIDERATIONS/REASONABLENESS
This property abuts property recently zoned for the
same combination as is being requested. Surrounding
land uses suggest its appropriateness, and the
April 29, 1980
Item No. 5 - Continued
extraterritorial plan indicates this area for
industrial development. Staff is concerned about the
proposal for "C-3," feeling that access is not quite
what is anticipated to be needed to serve 45 acres of
commercial development.
9. STANDARDS OF QUALITY
No standards of quality have been addressed.
10. TRAFFIC AND STREET RIGHT-OF-WAY
The only right-of-way issue is Mabelvale Pike. It is
carried as a minor arterial on the Master Street Plan,
requiring an 80' right-of-way. Staff estimates that
the applicant would be required to provide an easement
deed for ten feet. He has agreed to do so. Access to
the commercial portion of the request is problematical,
due to the design of the Mabelvale Interchange.
ANALYSIS
The extraterritorial plan indicates that this area should be
developed for industrial use. Access to the commercial
development proposed appears inadequate. The addition of 45
acres of commercial zoning to the 20 acres recently
committed to the east seems excessive.
Because of questions raised by neighboring owners at the
March meeting, the staff revisited the site and reviewed
available data on the flooding issue. In our opinion, the
flooding described by opponents of this request is not a
result of the Martin property and would not be exacerbated
by its development.
RECOMMENDATION:
Staff recommends approval of the "I-2" portion of the
request as filed and a recommendation for approval of "I-1"
on the portion requested for "C-3" General Commercial.
April 29, 1980
Item No. 5 - Z-3459 - DEFERRED
Owner: Martin Industrial Park, Inc. and
George C. Martin, Trustee
Applicant: W. S. Mitchell
Request: Rezone to "C-3" General Commercial
and "I-2" Light Indsustrial
Purpose: Mixed use development
Existing Zoning: 11R-2" Single Family
Location: Southeast corner of I-30 and
Mabelvale Interchange
Site Characteristics: Wooded
Size: 119.65 acres +
Existing Land Use: Large vacant area, having only
Mr. Martin's house
Abutting Land Use North - Public, Zoned "R-2"
Zoning: South - Residential, Zoned "R-2"
East - Vacant and Industrial,
Zoned "R-2"
West - Residential, Zoned "R-2"
Zoninq History: None
Applicable Regulations: Zoning and Subdivision Ordinances
FACTUAL INFORMATION
April 29, 1980
Item 5
1. NEED AND/OR DEMAND
This tract abuts the I-30 frontage road on the north
and the Missouri Pacific Railroad on the south. The
property just to the east was recently zoned to
a combination of commercial and industrial districts.
There is no specific proposal for development at this
time.
20 COMPATIBILITY WITH MUNICIPAL PLANS
Only the commercial portion of the request is not
compatible with the extraterritorial plan. This plan
calls for the entire tract to be used for industrial
purposes in the long term.
3. EFFECT ON ENVIRONS
While no truly environmental impacts are expected,
there seems to be no doubt that the eventual
development of this 119 acre tract will have
significant meaning for the surrounding properties.
There is no particular expectation that the future
impacts will be especially harmful.
4. NEIGHBORHOOD POSITION
Several neighbors have expressed opposition.
5. PUBLIC SERVICES/EFFECT ON
No adverse comments have been received.
6. UTILITIES/EFFECT ON
No adverse comments have been received.
7. EFFECT ON PUBLIC FINANCES
Logically, one must assume that the development of this
property would add significantly to the City's tax
base. Offsetting public costs would be minimal.
8. LEGAL CONSIDERATIONS/REASONABLENESS
This property abuts property recently zoned for the
same combination as is being requested. Surrounding
land uses suggest its appropriateness, and the
April 29, 1980
Item No. 5 - Continued
extraterritorial plan indicates this area for
industrial development. Staff is concerned about the
proposal for "C-3," feeling that access is not quite
what is anticipated to be needed to serve 45 acres of
commercial development.
9. STANDARDS OF QUALITY
No standards of quality have been addressed.
10. TRAFFIC AND STREET RIGHT-OF-WAY
The only right-of-way issue is Mabelvale Pike. It is
carried as a minor arterial on the Master Street Plan,
requiring an 80' right-of-way. Staff estimates that
the applicant would be required to provide an easement
deed for ten feet. He has agreed to do so. Access to
the commercial portion of the request is problematical,
due to the design of the Mabelvale Interchange.
ANALYSIS
The extraterritorial plan indicates that this area should be
developed for industrial use. Access to the commercial
development proposed appears inadequate. The addition of 45
acres of commercial zoning to the 20 acres recently
committed to the east seems excessive.
Because of questions raised by neighboring owners at the
March meeting, the staff revisited the site and reviewed
available data on the flooding issue. In our opinion, the
flooding described by opponents of this request is not a
result of the Martin property and would not be exacerbated
by its development.
STAFF RECOMMENDATION:
Staff recommends approval of the "I-2" portion of the
request as filed and a recommendation for approval of "I-1"
on the portion requested for "C-3" General Commercial.
COMMISSION ACTION:
The applicant was present, and there were no objectors.
The applicant presented an amended proposal in connection
with the previous neighborhood opposition which he had
worked out with those objecting neighbors. The amendment
consisted of the following:
April 29, 1980
Item No. 5 - Continued
In the amount of acreage established for the "C-3" requested
which would reduce the total requesters "C-3" zoning to
approximately 23 acres and to provide a 100' residential
zoned buffer along the rear of those properties which are on
Mavis Circle which abut the property under consideration.
There was a discussion of the
that everyone understood what
maintained its position that
was appropriate for the north
amendment merely to assure
was involved. The staff
rather than "C-3" that
part of the property.
After a lengthy discussion of the merits of "C-3" vs. "I-1"
and a variety of other considerations, the Commission moved
to approve the request as amended by the applicant. The
motion passed: 7 ayes, 3 noes and 1 absent.