HomeMy WebLinkAboutCCI_000066Public works Review Comments
❑ Board of Adjustment D Planning Commission'
Agenda Date: 1/5/2017
Z File Number LA-0056-A
Colonel Glenn -Lawson Rd Advanced Grading Varia NWC Colonel Glenn Rd and Lawson Rd
1 A grading permit in accordance with section 29-186 (c) & (d) will be required prior to any land
clearing or grading activities at the site. Other than residential subdivisions, site grading and drainage
plans must be submitted and.approved prior to the start of construction.
2 Storm water, detention ordinance applies to this property. Show the proposed location for stormwater
detention facilities on the grading plan.
3 If disturbed area is Lor more acres, obtain a NPDES storm water permit from the Arkansas
Department of Environmental Quality prior to the start of construction.
4 Damage to public and private property due to haulingoperations or operation of construction related
equipment from a nearby construction site shall be repaired by the responsible party prior to issuance-
of a certificate of occupancy.
5 P Sec. 29-197(2), the grading shall be expeditously completed in a time frame not to exceed one (1)'
ear in duration from the time work commences to installation of all final erosion control measures
and vegetation.
6 Provide visual screening of the completed area by providing undisturbed buffer strips or earthen
berms. Per Sec. 29-197(3) provide line of sight illustrations from adjacent street(s) and properties for
review, by the Planning Commission. The width of the temporary buffer strips shall be 6% of the lot
width and depth. The minimum width shall be'50 ft where the. subject property is adjacent to other
properties. The minimum width shall be 80 ft where the subject property is adjacent to arterial
streets (Col. Glenn Road). In no event shall these buffers be less than the width of the permanent
buffers required for the development. The maximum buffer width shall not exceed 100 ft. The
elevation of the top of berms :is determined by the elevation required to obstruct visibility.
7 Construction access points should be shown on the grading plan. A curved or angled road design
should be provided to limit the visibility of the interior grading work from adjacent streets.
8 Per Sec. 29497(11), a permanent vegetative cover of suitable perennial grass shall be established
over all disturbed areas. Where indicated by soil tests, pH adjustments and addition of fertilizer may
be required.
9 Per Sec. 29-197(12), all erosion and stabilization controls, including permanent vegetation and
plantings and stormwater detention systems are to be maintained by the responsible part for a period
of 2 years following completion of site grading.
10 Per Seca 29-197(12), periodic mowing, generally 2 times per year or more often if required by CLR
shall be provided to encourage, perennial grass growth.
11 Per Seca 29-197(13), maintenance for the 2 year period shall be guaranteed through posting of cash,
surety bond or letter of credit as referenced in Sec. 31-431(2) at the time of final inspection of the
grading activities.
Monday, August17, 2020 Page l of 2
1
r
12 Per Sec. 29-197(14), all required federal, state, and local permits and approvals shall be obtained
prior to commencement of land alteration activities.
13 Public works staff must be contacted for inspection for final approval of site stabilization prior to
acceptance and relinquishment of maintenance bond.
14 Staked orange fencing must be installed along the open space undisturbed buffer areas during
construction to prevent access to these buffer areas.
15 At the completion of the land alteration activities, a minimum six (6),inches of suitable topsoil shall
be placed over all disturbed areas and permanent vegetative cover established.
16 Where is the proposed destination of the fill material?,
Monday, August 17, 2020 Page 2 of 2