Z File Number LA-0056-B Colonel Glenn-Lawson Rd Adv Grade Variance NWC Col Glenn Rd and Lawson Rd
1 The expired grading permit in accordance with section 29-186 (c) & (d) will be required to be renewed and erosion and sediment controls reworked as needed prior to the resuming of any grading activities at the site. Staff will reinspect the site prior to permit renewal.
2 Storm water detention ordinance applies to this property. Show the proposed location for stormwater detention facilities on the grading plan.
3 If disturbed area is 1 or more acres, obtain a NPDES storm water permit from the Arkansas Department of Environmental Quality prior to the start of construction.
4 Damage to public and private property due to hauling operations or operation of construction related equipment from a nearby construction site shall be repaired by the responsible
party prior to issuance of a certificate of occupancy.
5 Per Sec. 29-197(2), the grading shall be expeditously completed in a time frame not to exceed one (1) year in duration from the time work commences to installation of all final
erosion control measures and vegetation.
6 Provide visual screening of the completed area by providing undisturbed buffer strips or earthen berms. Plan shows a screening berm.
7 Construction access points should be shown on the grading plan. A curved or angled road design should be provided to limit the visibility of the interior grading work from adjacent
streets. Access shown on plan.
8 Per Sec. 29-197(11), a permanent vegetative cover of suitable perennial grass shall be established over all disturbed areas. Where indicated by soil tests, pH adjustments and addition
of fertilizer may be required.
9 Per Sec. 29-197(12), all erosion and stabilization controls, including permanent vegetation and plantings and stormwater detention systems are to be maintained by the
responsible part for a period of 2 years following completion of site grading.
10 Per Sec. 29-197(12), periodic mowing, generally 2 times per year or more often if required by CLR shall be provided to encourage perennial grass growth.
11 Per Sec. 29-197(13), maintenance for the 2 year period shall be guaranteed through posting of cash, surety bond or letter of credit as referenced in Sec. 31-431(2) at the
time of final inspection of the grading activities.
12 The application fee of $75 is due for payment to CLR Public Works Dept. Deliver payment to Vince Floriani.
13 Obtain a sign from CLR Public Works Dept. Vince Floriani to post at the site viewable by the public.
Friday, August 28, 2020 Page 1 of 2
14 Several water quality complaints have been received from adjacent property owners. The existing erosion and sediment controls must be maintained and reworked as needed to reduce sediment loss to the maximum extent practicable. A diversion ditch should be constructed on the northside of Colonel Glenn Road to the existing ditches along with the existing ditching cleaned.