October 12, 2020
Mr. Timothy E. Daters P.E.
President
White-Daters & Associates, Inc.
24 Rahling Circle
Little Rock, AR 72223
Re: P2064
Traffic Analysis Summary
WOODLANDS EDGE
NORTH SLOPE
Little Rock, Arkansas
Mr. Daters:
Peters & Associates Engineers, Inc. prepared this summary of traffic analysis related to the development of
Woodlands Edge North Slope and access at the intersection of Kanis Road and Woodlands Trail. It is
understood that the City of Little Rock has plans for improvements to Kanis Road in the vicinity, but the
likely schedule for that improvement project will likely not be before development of the Woodlands Edge
North Slope.
The traffic analysis included conducting 24-hour vehicular turning movement counts at the intersection of
Kanis Road and Woodlands Trail. These count data were used as the base to project future traffic volumes for
various analysis scenarios. The analysis included the following scenarios:
1) Existing traffic volumes and intersection lane geometry.
2) An alternate development condition with a different residential lot configuration than the proposed
Woodlands Edge North Slope plan and with no commercial components.
3) A condition of development per the Woodlands Edge North Slope plan but without the commercial
component.
4) Woodlands Edge North Slope plan as proposed.
5a) Woodlands Edge North Slope plan as proposed with Kanis Road widening to accommodate a
westbound left turn lane and traffic signal control.
The traffic operational analysis was done for AM and PM peak traffic periods. Traffic signal warrants
analysis for Scenario 5a indicates warrant criteria is projected to be met for those conditions.
The traffic operational analysis results and traffic signal warrants analysis results are summarized below:
Mr. Tim Daters, P.E.
October 12, 2020
Page 2 of 3
Eastbound Left-TurnEastbound ThruEastbound Right-TurnWestbound Left-TurnWestbound ThruWestbound Right-TurnNorthbound Left-TurnNorthbound ThruNorthbound Right-TurnSouthbound Left-TurnSouthbound ThruSouthbound Right-TurnOverall IntersectionINTERSECTION PEAK HR
AM A A C B n/a 3.8
PM A A D B n/a 2.6
Eastbound Left-TurnEastbound ThruEastbound Right-TurnWestbound Left-TurnWestbound ThruWestbound Right-TurnNorthbound Left-TurnNorthbound ThruNorthbound Right-TurnSouthbound Left-TurnSouthbound ThruSouthbound Right-TurnOverall IntersectionINTERSECTION PEAK HR
AM A A D B n/a 4.6
PM A A F B n/a 3.5
Eastbound Left-TurnEastbound ThruEastbound Right-TurnWestbound Left-TurnWestbound ThruWestbound Right-TurnNorthbound Left-TurnNorthbound ThruNorthbound Right-TurnSouthbound Left-TurnSouthbound ThruSouthbound Right-TurnOverall IntersectionINTERSECTION PEAK HR
AM A A D B n/a 6.2
PM A A F B n/a 15.1
Eastbound Left-TurnEastbound ThruEastbound Right-TurnWestbound Left-TurnWestbound ThruWestbound Right-TurnNorthbound Left-TurnNorthbound ThruNorthbound Right-TurnSouthbound Left-TurnSouthbound ThruSouthbound Right-TurnOverall IntersectionINTERSECTION PEAK HR
AM A A E B n/a 7.0
PM A A F B n/a 14.1
Eastbound Left-TurnEastbound ThruEastbound Right-TurnWestbound Left-TurnWestbound ThruWestbound Right-TurnNorthbound Left-TurnNorthbound ThruNorthbound Right-TurnSouthbound Left-TurnSouthbound ThruSouthbound Right-TurnOverall IntersectionINTERSECTION PEAK HR
AM C A C A C A B 14.7
PM C A C A C A B 15.5Avg. Control Delay Seconds / VehiclePEAK HOUR - LEVEL OF SERVICE Avg. Control Delay Seconds / VehicleEXISTING TRAFFIC CONDITIONS
Traffic ControlTraffic ControlPEAK HOUR - LEVEL OF SERVICE
Kanis Road and Woodlands Trail "STOP" SIGN
PROJECTED TRAFFIC CONDITIONS
SCENARIO 2
(Existing Lane Geometry and Traffic Control)
A
A
Kanis Road and Woodlands Trail
Avg. Control Delay Seconds / Vehicle"STOP" SIGN
PEAK HOUR - LEVEL OF SERVICE
A
A
PROJECTED TRAFFIC CONDITIONS
SCENARIO 3
(Existing Lane Geometry and Traffic Control)Traffic ControlAvg. Control Delay Seconds / VehiclePEAK HOUR - LEVEL OF SERVICE
A
A
PROJECTED TRAFFIC CONDITIONS
SCENARIO 4
(Existing Lane Geometry and Traffic Control)Traffic ControlKanis Road and Woodlands Trail "STOP" SIGN
A
AKanis Road and Woodlands Trail "STOP" SIGN
Avg. Control Delay Seconds / VehiclePEAK HOUR - LEVEL OF SERVICE
PROJECTED TRAFFIC CONDITIONS
SCENARIO 5a
WITH TRAFFIC SIGNAL
(With Addition of WB Left-Turn Lane)Traffic ControlKanis Road and Woodlands Trail SIGNAL
Mr. Tim Daters, P.E.
October 12, 2020
Page 3 of 3
Below is a copy of the Woodlands Edge North Slope plan:
The results of the traffic analysis indicate that with the development of Woodlands Edge North Slope as
proposed and with widening of Kanis Road to provide a westbound left turn lane and traffic signal control,
acceptable traffic operational can be achieved at the intersection of Kanis Road and Woodlands Trail.
Please let me know if you need additional information or comment.
Sincerely,
PETERS & ASSOCIATES, ENGINEERS, INC.
Ernest J. Peters, P.E.
President