11569RESOLUTION NO. 11,569
0
A RESOLUTION AWARDING A CONTRACT
TO GENE SUMMERS CONSTRUCTION FOR
CONSTRUCTING IMPROVEMENT TO HIGH
DRIVE
WHEREAS, improvements are needed on high Drive to improve traffic flow, drainage,
and enhance public safety,
AND, Gene Summers Construction submitted the lowest bid meeting specifications, bid
number 03 -246.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF DIRECTORS OF
THE CITY OF LITTLE ROCK, ARKANSAS:
SECTION 1. The City Manager is hereby authorized to award a contract and execute an
agreement with Gene Summers Construction in an amount not to exceed $152,352.00
($138,502.15 plus 10% contingency) for the construction of improvements to High Drive.
SECTION 2. Funding for the project is available from fund CDBG- CO2 -G562.
SECTION 3. This resolution will be in full force and effect from and after the date of its
adoption.
ADOPTED: August 4, 2003
ATTEST:
CY WOOD
Ci Clerk
APPROVED:
SIAM
Mayor