3 RESOLUTION NO. 9.899
4
5 A RESOLUTION AUTHORIZING THE CITY MANAGER TO
6
7 ENTER INTO A CONTRACT WITH GRIMES CONSULTING
8 ENGINEERS, INC. IN THE AMOUNT OF $30,842 TO PROVIDE
9 ENGINEERING SERVICES FOR THE RECONSTRUCTION OF
10
11 SPRINGER BOULEVARD FROM GILLAM PARK ROAD TO
12 THE UNION PACIFIC RAILROAD, AND FOR THE PLATTING
13
14 OF THREE LOTS ON THE NORTH SIDE OF WEST 23RD
15 STREET EAST OF WALKER STREET FOR THE
16 CONSTRUCTION OF AFFORDABLE HOMES, A 22ND YEAR
17
18 CDBG PROJECT.
19
20 WHEREAS, the project is consistent with the City's Consolidated Plan; and
21
22 WHEREAS, $281,460 was allocated by the Board in the CDBG 22nd Year
23 Program for engineering and constriction of the described package of public facilities
24
25 improvements in the Granite Mountain and John Barrow Road Redevelopment
26 (CDBG) areas.
27 NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF
28
29 DIRECTORS OF THE CITY OF LITTLE ROCK, ARKANSAS:
30 SECTION 1. The City Manager is authorized to enter into a contract with
31
Grimes Consulting Engineers, Inc., the most qualified bidder meeting specifications,
32
33 in an amount not to exceed $30,482 to provide engineering services for the
34 reconstruction of Springer Boulevard from Gillam Park Road to the Union Pacific
35
36 Railroad right -of -way, and for the platting of three lots on the north side of West 23rd
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Street east of Walker Street for the construction of affordable homes, and the design
of related infrastructure adjacent to the lots.
SECTION 2. Funding in the amount of $30,842 is available for engineeringg
from the Community Development Block Grant Program and is budgeted for in the
22nd Year Consolidated Plan.
ADOPTED: January 21, 1997